This is the productivity of construction works, including quantity, labor, and duration, which is very helpful information for all site engineers.
Productivity, Labor, and Duration for Activities
Excavation (Manual)
- Quantity: 8–10 cubic meters/day per laborer
- Labor: 10–15 laborers (for larger sites)
- Duration: As per the area/volume to excavate
Mechanical Excavation
- Quantity: 80–120 cubic meters/day (using an excavator)
- Labor: 1 operator, 2 helpers
- Duration: Based on excavation size
Manual Backfilling from Available Soil
- Quantity: 12 cubic meters/labor/day
- Labor: 6–8 laborers
- Duration: Based on total area/volume
Backfilling from Brought-Out Soil
- Quantity: 15 cubic meters/labor/day
- Labor: 5 laborers (excluding transport equipment labor)
- Duration: Based on volume and transport logistics
Sand Filling
- Quantity: 20 cubic meters/day (manual filling)
- Labor: 4–5 laborers
- Duration: Based on area and thickness
Anti-Termite Treatment
- Quantity: 1,000–1,200 square meters/day (spray application)
- Labor: 4 workers (including one technician)
- Duration: Based on the area
PCC Concrete Casting
- Quantity: 15 cubic meters/day (manual mixing)
- Labor: 6 workers (2 masons, 4 helpers)
- Duration: Adjust to total volume
Formwork - Foundation
- Quantity: 20–30 square meters/day (per team)
- Labor: 4–6 carpenters, 2 helpers
- Duration: Depends on total formwork area
Formwork - Column & Shear Wall
- Quantity: 15–20 square meters/day (per team)
- Labor: 5 carpenters, 3 helpers
- Duration: Adjust to design complexity
Formwork - Beam & Slab
- Quantity: 30–40 square meters/day
- Labor: 6 carpenters, 4 helpers
- Duration: Depends on total shuttering area
Reinforcement Binding
- Quantity: 1 metric ton/day
- Labor: 4 workers (2 skilled, 2 helpers)
- Duration: Based on rebar tonnage
Precast Concrete
- Quantity: 5–10 precast elements/day
- Labor: 6–8 workers (skilled + helpers)
- Duration: Varies by piece complexity
Burnt Clay Brickwork
- Quantity: 1–1.2 cubic meters/mason/day
- Labor: 2 masons, 2 helpers
- Duration: Based on wall area
Fly Ash Brickwork
- Quantity: 1.5–1.8 cubic meters/mason/day
- Labor: 2 masons, 2 helpers
- Duration: Based on wall area
AAC Blockwork
- Quantity: 2 cubic meters/mason/day
- Labor: 2 masons, 2 helpers
- Duration: Based on wall area
Random Rubble Masonry
- Quantity: 1–1.2 cubic meters/mason/day
- Labor: 2 masons, 3 helpers
- Duration: Depends on volume
Internal Plaster
- Quantity: 10 square meters/mason/day
- Labor: 2 masons, 2 helpers
- Duration: Based on surface area
Sunken Filling with AAC Block
- Quantity: 8–10 cubic meters/day
- Labor: 4 workers
- Duration: Based on sunken area
Sunken Filling with Lightweight Concrete
- Quantity: 10–12 cubic meters/day
- Labor: 5 workers
- Duration: Depends on area
Waterproofing - Tapecrete
- Quantity: 50 square meters/day
- Labor: 3 workers (1 applicator, 2 helpers)
- Duration: Based on area
- Waterproofing - Injection Grouting
- Quantity: 30–40 injection points/day
- Labor: 4 workers (1 technician, 3 helpers)
- Duration: Based on number of points
- Thermal Insulation - XPS Board Fixing
- Quantity: 60–70 square meters/day
- Labor: 3 workers
- Duration: Depends on total insulation area
- Making of Khurras
- Quantity: 15–20 khurras/day
- Labor: 3 workers (1 mason, 2 helpers)
- Duration: Based on required numbers
- Wall Surface Preparation
- Quantity: 200–250 square meters/day
- Labor: 4 workers
- Duration: Based on surface area
- POP Works
- Quantity: 40–50 square meters/day
- Labor: 3 workers (1 applicator, 2 helpers)
- Duration: Depends on area
- Paint Work
- Quantity: 120–150 square meters/day (1 coat)
- Labor: 3 painters
- Duration: Based on number of coats and surface area
- Putty Work
- Quantity: 80–100 square meters/day
- Labor: 3 workers (1 skilled, 2 helpers)
- Duration: Depends on surface area
- Primer Work
- Quantity: 120–150 square meters/day (1 coat)
- Labor: 2 painters
- Duration: Based on number of coats and area
- Textured Paint - Roller
- Quantity: 60–80 square meters/day
- Labor: 4 workers (2 skilled, 2 helpers)
- Duration: Based on wall area
- White Wash
- Quantity: 200–250 square meters/day
- Labor: 2 painters
- Duration: Based on coats and area
- Kota Flooring
- Quantity: 10–12 square meters/day
- Labor: 2 masons, 2 helpers
- Duration: Based on floor area
- Marble Flooring
- Quantity: 8–10 square meters/day
- Labor: 2 masons, 2 helpers
- Duration: Based on total flooring area
- Stone Flooring
- Quantity: 6–8 square meters/day
- Labor: 2 masons, 3 helpers
- Duration: Based on flooring area
- Sandstone Flooring
- Quantity: 8–10 square meters/day
- Labor: 2 masons, 3 helpers
- Duration: Depends on total area
- Granite Flooring
- Quantity: 6–8 square meters/day
- Labor: 2 masons, 3 helpers
- Duration: Based on floor area
- Tile Flooring
- Quantity: 15–20 square meters/day
- Labor: 2 masons, 2 helpers
- Duration: Based on total area
- Terrazzo Flooring
- Quantity: 10–12 square meters/day
- Labor: 3 workers
- Duration: Depends on flooring area
- Wooden Flooring
- Quantity: 15–20 square meters/day
- Labor: 2 carpenters, 2 helpers
- Duration: Depends on total area
- Grid Tile False Ceiling
- Quantity: 30–40 square meters/day
- Labor: 3 workers (2 skilled, 1 helper)
- Duration: Based on ceiling area
- Gypsum Board False Ceiling
- Quantity: 20–25 square meters/day
- Labor: 4 workers
- Duration: Depends on ceiling area
- Loose Furniture Installation
- Quantity: 6–8 units/day
- Labor: 3 workers
- Duration: Based on the number of units
- Aluminium Door Frame Fixing
- Quantity: 3–4 frames/day
- Labor: 2 workers
- Duration: Based on number of frames
- MS Door Frame Fixing
- Quantity: 2–3 frames/day
- Labor: 2 workers
- Duration: Based on frame numbers
- Wooden Door Fixing
- Quantity: 2–3 doors/day
- Labor: 2 carpenters, 1 helper
- Duration: Based on door quantity
- Aluminium Door Fixing
- Quantity: 3–4 doors/day
- Labor: 2 workers
- Duration: Depends on total doors
- Wooden Window Frame Fixing
- Quantity: 5–6 frames/day
- Labor: 2 carpenters, 1 helper
- Duration: Based on total frames
- Aluminium Window Frame Fixing
- Quantity: 5–6 frames/day
- Labor: 2 workers
- Duration: Based on total windows
- Glass Windows Fixing
- Quantity: 6–8 windows/day
- Labor: 3 workers
- Duration: Depends on window quantity
- Flush Door Installation
- Quantity: 4–5 doors/day
- Labor: 2 carpenters, 1 helper
- Duration: Based on total doors
- Fire Door Installation
- Quantity: 3–4 doors/day
- Labor: 3 workers
- Duration: Based on total fire doors
Productivity, Labor, and Duration (Continued)
- Door Hardware Fixing
- Quantity: 8–10 doors/day
- Labor: 2 workers
- Duration: Based on total doors
- Façade - Brick Tile
- Quantity: 15–20 square meters/day
- Labor: 3 workers (1 skilled, 2 helpers)
- Duration: Depends on façade area
- Façade - Terracotta Jali
- Quantity: 10–15 square meters/day
- Labor: 4 workers (2 skilled, 2 helpers)
- Duration: Based on total area
- MS Railing Work
- Quantity: 6–8 running meters/day
- Labor: 3 workers (2 fabricators, 1 helper)
- Duration: Depends on railing length
- Glass Railing Work
- Quantity: 5–6 running meters/day
- Labor: 4 workers (2 skilled, 2 helpers)
- Duration: Based on total railing length
- SS Railing Work
- Quantity: 6–8 running meters/day
- Labor: 3 workers
- Duration: Based on railing length
- External Plaster
- Quantity: 70–100 square meters/day
- Labor: 5 workers (2 masons, 3 helpers)
- Duration: Depends on wall surface
- Dry Stone Pitching
- Quantity: 8–10 square meters/day
- Labor: 4 workers
- Duration: Based on total area
- Laminate Fixing
- Quantity: 6–8 square meters/day
- Labor: 2 carpenters, 1 helper
- Duration: Based on laminate area
- Gypsum Board Partition Fixing
- Quantity: 20–25 square meters/day
- Labor: 3 workers
- Duration: Based on partition area
- Veneer Paneling
- Quantity: 5–8 square meters/day
- Labor: 2 carpenters, 1 helper
- Duration: Based on total area
- Pelmet Installation (300 mm)
- Quantity: 10–12 running meters/day
- Labor: 2 carpenters, 1 helper
- Duration: Based on total length
- Rolling Shutter Installation (3M x 3M)
- Quantity: 1–2 shutters/day
- Labor: 4 workers (2 fitters, 2 helpers)
- Duration: Based on total shutters
- MS Work - Fabrication
- Quantity: 150–200 kilograms/day
- Labor: 5 workers
- Duration: Based on total weight
- MS Work - Installation
- Quantity: 200–300 kilograms/day
- Labor: 5 workers
- Duration: Based on total weight
- Tremix Flooring
- Quantity: 40–50 square meters/day
- Labor: 4 workers
- Duration: Depends on floor area
- Vitrified Tile Flooring
- Quantity: 15–20 square meters/day
- Labor: 3 workers (2 masons, 1 helper)
- Duration: Based on total area
- Ceramic Tile Flooring
- Quantity: 15–20 square meters/day
- Labor: 3 workers (2 masons, 1 helper)
- Duration: Based on flooring area
- Counter Top Stone Fixing
- Quantity: 4–6 countertops/day
- Labor: 3 workers (1 mason, 2 helpers)
- Duration: Based on total countertops
- Stone Edge Moulding
- Quantity: 10–12 running meters/day
- Labor: 2 workers
- Duration: Based on edge length
- Floor Polishing
- Quantity: 30–40 square meters/day
- Labor: 3 workers (2 polishers, 1 helper)
- Duration: Based on floor area
- POP Floor Protection
- Quantity: 50–60 square meters/day
- Labor: 2 workers
- Duration: Depends on total area
- PVC Sheet Floor Protection
- Quantity: 70–80 square meters/day
- Labor: 2 workers
- Duration: Based on total area
- Installation of Sanitary Fixtures
- Quantity: 6–8 fixtures/day
- Labor: 2 plumbers, 1 helper
- Duration: Based on total fixtures
- Installation of Chinaware
- Quantity: 5–7 units/day
- Labor: 3 workers (2 plumbers, 1 helper)
- Duration: Based on units
- Installation of Concealed Items
- Quantity: 5–7 units/day
- Labor: 3 workers
- Duration: Depends on concealed units
- Fixing of Toilet Cubicle/Partition
- Quantity: 3–5 cubicles/day
- Labor: 4 workers
- Duration: Based on total cubicles
- Installation of Toilet Accessories/Machinery Equipment
- Quantity: 6–8 units/day
- Labor: 3 workers (2 plumbers, 1 helper)
- Duration: Based on equipment
- CPVC Pipe Laying
- Quantity: 60–80 running meters/day
- Labor: 4 workers
- Duration: Based on total length
- UPVC Pipe Laying
- Quantity: 50–70 running meters/day
- Labor: 4 workers
- Duration: Based on pipe length
- G.I. Pipe Laying
- Quantity: 50–70 running meters/day
- Labor: 4 workers (2 skilled, 2 helpers)
- Duration: Based on pipe length
- Copper Pipe Laying
- Quantity: 40–50 running meters/day
- Labor: 3 workers (1 skilled, 2 helpers)
- Duration: Based on pipe length
- DWC Pipe Laying
- Quantity: 80–100 running meters/day
- Labor: 5 workers (2 skilled, 3 helpers)
- Duration: Based on total length
- HDPE Pipe Laying
- Quantity: 70–90 running meters/day
- Labor: 4 workers
- Duration: Depends on total pipe length
- RCC Pipe Laying
- Quantity: 25–30 running meters/day
- Labor: 6 workers (2 skilled, 4 helpers)
- Duration: Based on total length
- C.I. Pipe Laying
- Quantity: 30–40 running meters/day
- Labor: 4 workers
- Duration: Based on pipe length
- SS Pipe Laying
- Quantity: 30–40 running meters/day
- Labor: 4 workers (2 skilled, 2 helpers)
- Duration: Based on total length
- Plumbing 1st Fix
- Quantity: 3–5 points/day
- Labor: 2 plumbers, 1 helper
- Duration: Based on total points
- Trap Fixing
- Quantity: 6–8 traps/day
- Labor: 3 workers (2 plumbers, 1 helper)
- Duration: Based on total traps
- Fixing of Floor Drain
- Quantity: 8–10 drains/day
- Labor: 2 workers
- Duration: Based on total drains
- Thermal Insulation of Pipes
- Quantity: 50–70 running meters/day
- Labor: 3 workers (2 skilled, 1 helper)
- Duration: Based on total length
- Cinder Raised Flooring
- Quantity: 15–20 square meters/day
- Labor: 5 workers
- Duration: Based on area
- Modular Access Raised Flooring
- Quantity: 25–30 square meters/day
- Labor: 4 workers (2 skilled, 2 helpers)
- Duration: Based on total area
- Installation of Water Flow Meter
- Quantity: 4–6 meters/day
- Labor: 2 plumbers, 1 helper
- Duration: Based on meters
- Gully Trap Fixing
- Quantity: 8–10 traps/day
- Labor: 3 workers (2 masons, 1 helper)
- Duration: Based on traps
- Excavation for External Plumbing
- Quantity: 10–15 cubic meters/day
- Labor: 4 workers (2 skilled, 2 helpers)
- Duration: Based on trench volume
- Haunching
- Quantity: 12–15 running meters/day
- Labor: 3 workers
- Duration: Based on haunch length
- Paver Block Laying
- Quantity: 20–25 square meters/day
- Labor: 4 workers (2 masons, 2 helpers)
- Duration: Based on area
- Manhole Construction
- Quantity: 1–2 manholes/day
- Labor: 5 workers (2 masons, 3 helpers)
- Duration: Based on number of manholes
- Catch Basin Construction
- Quantity: 1 basin/day
- Labor: 4 workers
- Duration: Based on number of basins
- Rainwater Harvesting Pit Construction
- Quantity: 1 pit/day
- Labor: 6 workers
- Duration: Based on number of pits
- De-Silting Chamber Construction
- Quantity: 1 chamber/day
- Labor: 4 workers (2 skilled, 2 helpers)
- Duration: Based on total chambers
- Manhole SFRC Frame & Cover Fixing
- Quantity: 2–3 covers/day
- Labor: 3 workers
- Duration: Based on total covers
- Manhole D.I. Frame & Cover Fixing
- Quantity: 2–3 covers/day
- Labor: 3 workers
- Duration: Based on total covers
- Installation of Sump Pump
- Quantity: 1–2 pumps/day
- Labor: 4 workers (2 skilled, 2 helpers)
- Duration: Based on number of pumps
- Installation of Fire Pump
- Quantity: 1 pump/day
- Labor: 5 workers (2 skilled, 3 helpers)
- Duration: Based on total pumps
- Installation of Plumbing Water Supply Pump
- Quantity: 1–2 pumps/day
- Labor: 4 workers (2 skilled, 2 helpers)
- Duration: Based on number of pumps
- Installation of Domestic Water Submersible Pump
- Quantity: 1–2 pumps/day
- Labor: 4 workers
- Duration: Based on total pumps
- Making Connection of Sewer Line with Municipality Line
- Quantity: 1 connection/day
- Labor: 6 workers (3 skilled, 3 helpers)
- Duration: Based on connections
- Making Connection of Sewer Line with STP
- Quantity: 1 connection/day
- Labor: 6 workers (3 skilled, 3 helpers)
- Duration: Based on total connections