Comprehensive Productivity and Labor Estimation for Construction Activities

Gggg


This is the productivity of construction works, including quantity, labor, and duration, which is very helpful information for all site engineers.


Productivity, Labor, and Duration for Activities

  1. Excavation (Manual)

    • Quantity: 8–10 cubic meters/day per laborer
    • Labor: 10–15 laborers (for larger sites)
    • Duration: As per the area/volume to excavate
  2. Mechanical Excavation

    • Quantity: 80–120 cubic meters/day (using an excavator)
    • Labor: 1 operator, 2 helpers
    • Duration: Based on excavation size
  3. Manual Backfilling from Available Soil

    • Quantity: 12 cubic meters/labor/day
    • Labor: 6–8 laborers
    • Duration: Based on total area/volume
  4. Backfilling from Brought-Out Soil

    • Quantity: 15 cubic meters/labor/day
    • Labor: 5 laborers (excluding transport equipment labor)
    • Duration: Based on volume and transport logistics
  5. Sand Filling

    • Quantity: 20 cubic meters/day (manual filling)
    • Labor: 4–5 laborers
    • Duration: Based on area and thickness
  6. Anti-Termite Treatment

    • Quantity: 1,000–1,200 square meters/day (spray application)
    • Labor: 4 workers (including one technician)
    • Duration: Based on the area
  7. PCC Concrete Casting

    • Quantity: 15 cubic meters/day (manual mixing)
    • Labor: 6 workers (2 masons, 4 helpers)
    • Duration: Adjust to total volume
  8. Formwork - Foundation

    • Quantity: 20–30 square meters/day (per team)
    • Labor: 4–6 carpenters, 2 helpers
    • Duration: Depends on total formwork area
  9. Formwork - Column & Shear Wall

    • Quantity: 15–20 square meters/day (per team)
    • Labor: 5 carpenters, 3 helpers
    • Duration: Adjust to design complexity
  10. Formwork - Beam & Slab

    • Quantity: 30–40 square meters/day
    • Labor: 6 carpenters, 4 helpers
    • Duration: Depends on total shuttering area
  11. Reinforcement Binding

    • Quantity: 1 metric ton/day
    • Labor: 4 workers (2 skilled, 2 helpers)
    • Duration: Based on rebar tonnage
  12. Precast Concrete

    • Quantity: 5–10 precast elements/day
    • Labor: 6–8 workers (skilled + helpers)
    • Duration: Varies by piece complexity
  13. Burnt Clay Brickwork

    • Quantity: 1–1.2 cubic meters/mason/day
    • Labor: 2 masons, 2 helpers
    • Duration: Based on wall area
  14. Fly Ash Brickwork

    • Quantity: 1.5–1.8 cubic meters/mason/day
    • Labor: 2 masons, 2 helpers
    • Duration: Based on wall area
  15. AAC Blockwork

    • Quantity: 2 cubic meters/mason/day
    • Labor: 2 masons, 2 helpers
    • Duration: Based on wall area
  16. Random Rubble Masonry

    • Quantity: 1–1.2 cubic meters/mason/day
    • Labor: 2 masons, 3 helpers
    • Duration: Depends on volume
  17. Internal Plaster

    • Quantity: 10 square meters/mason/day
    • Labor: 2 masons, 2 helpers
    • Duration: Based on surface area
  18. Sunken Filling with AAC Block

    • Quantity: 8–10 cubic meters/day
    • Labor: 4 workers
    • Duration: Based on sunken area
  19. Sunken Filling with Lightweight Concrete

    • Quantity: 10–12 cubic meters/day
    • Labor: 5 workers
    • Duration: Depends on area
  20. Waterproofing - Tapecrete

    • Quantity: 50 square meters/day
    • Labor: 3 workers (1 applicator, 2 helpers)
    • Duration: Based on area
  1. Waterproofing - Injection Grouting
  • Quantity: 30–40 injection points/day
  • Labor: 4 workers (1 technician, 3 helpers)
  • Duration: Based on number of points
  1. Thermal Insulation - XPS Board Fixing
  • Quantity: 60–70 square meters/day
  • Labor: 3 workers
  • Duration: Depends on total insulation area
  1. Making of Khurras
  • Quantity: 15–20 khurras/day
  • Labor: 3 workers (1 mason, 2 helpers)
  • Duration: Based on required numbers
  1. Wall Surface Preparation
  • Quantity: 200–250 square meters/day
  • Labor: 4 workers
  • Duration: Based on surface area
  1. POP Works
  • Quantity: 40–50 square meters/day
  • Labor: 3 workers (1 applicator, 2 helpers)
  • Duration: Depends on area
  1. Paint Work
  • Quantity: 120–150 square meters/day (1 coat)
  • Labor: 3 painters
  • Duration: Based on number of coats and surface area
  1. Putty Work
  • Quantity: 80–100 square meters/day
  • Labor: 3 workers (1 skilled, 2 helpers)
  • Duration: Depends on surface area
  1. Primer Work
  • Quantity: 120–150 square meters/day (1 coat)
  • Labor: 2 painters
  • Duration: Based on number of coats and area
  1. Textured Paint - Roller
  • Quantity: 60–80 square meters/day
  • Labor: 4 workers (2 skilled, 2 helpers)
  • Duration: Based on wall area
  1. White Wash
  • Quantity: 200–250 square meters/day
  • Labor: 2 painters
  • Duration: Based on coats and area
  1. Kota Flooring
  • Quantity: 10–12 square meters/day
  • Labor: 2 masons, 2 helpers
  • Duration: Based on floor area
  1. Marble Flooring
  • Quantity: 8–10 square meters/day
  • Labor: 2 masons, 2 helpers
  • Duration: Based on total flooring area
  1. Stone Flooring
  • Quantity: 6–8 square meters/day
  • Labor: 2 masons, 3 helpers
  • Duration: Based on flooring area
  1. Sandstone Flooring
  • Quantity: 8–10 square meters/day
  • Labor: 2 masons, 3 helpers
  • Duration: Depends on total area
  1. Granite Flooring
  • Quantity: 6–8 square meters/day
  • Labor: 2 masons, 3 helpers
  • Duration: Based on floor area
  1. Tile Flooring
  • Quantity: 15–20 square meters/day
  • Labor: 2 masons, 2 helpers
  • Duration: Based on total area
  1. Terrazzo Flooring
  • Quantity: 10–12 square meters/day
  • Labor: 3 workers
  • Duration: Depends on flooring area
  1. Wooden Flooring
  • Quantity: 15–20 square meters/day
  • Labor: 2 carpenters, 2 helpers
  • Duration: Depends on total area
  1. Grid Tile False Ceiling
  • Quantity: 30–40 square meters/day
  • Labor: 3 workers (2 skilled, 1 helper)
  • Duration: Based on ceiling area
  1. Gypsum Board False Ceiling
  • Quantity: 20–25 square meters/day
  • Labor: 4 workers
  • Duration: Depends on ceiling area
  1. Loose Furniture Installation
  • Quantity: 6–8 units/day
  • Labor: 3 workers
  • Duration: Based on the number of units
  1. Aluminium Door Frame Fixing
  • Quantity: 3–4 frames/day
  • Labor: 2 workers
  • Duration: Based on number of frames
  1. MS Door Frame Fixing
  • Quantity: 2–3 frames/day
  • Labor: 2 workers
  • Duration: Based on frame numbers
  1. Wooden Door Fixing
  • Quantity: 2–3 doors/day
  • Labor: 2 carpenters, 1 helper
  • Duration: Based on door quantity
  1. Aluminium Door Fixing
  • Quantity: 3–4 doors/day
  • Labor: 2 workers
  • Duration: Depends on total doors
  1. Wooden Window Frame Fixing
  • Quantity: 5–6 frames/day
  • Labor: 2 carpenters, 1 helper
  • Duration: Based on total frames
  1. Aluminium Window Frame Fixing
  • Quantity: 5–6 frames/day
  • Labor: 2 workers
  • Duration: Based on total windows
  1. Glass Windows Fixing
  • Quantity: 6–8 windows/day
  • Labor: 3 workers
  • Duration: Depends on window quantity
  1. Flush Door Installation
  • Quantity: 4–5 doors/day
  • Labor: 2 carpenters, 1 helper
  • Duration: Based on total doors
  1. Fire Door Installation
  • Quantity: 3–4 doors/day
  • Labor: 3 workers
  • Duration: Based on total fire doors

Productivity, Labor, and Duration (Continued)

  1. Door Hardware Fixing
  • Quantity: 8–10 doors/day
  • Labor: 2 workers
  • Duration: Based on total doors
  1. Façade - Brick Tile
  • Quantity: 15–20 square meters/day
  • Labor: 3 workers (1 skilled, 2 helpers)
  • Duration: Depends on façade area
  1. Façade - Terracotta Jali
  • Quantity: 10–15 square meters/day
  • Labor: 4 workers (2 skilled, 2 helpers)
  • Duration: Based on total area
  1. MS Railing Work
  • Quantity: 6–8 running meters/day
  • Labor: 3 workers (2 fabricators, 1 helper)
  • Duration: Depends on railing length
  1. Glass Railing Work
  • Quantity: 5–6 running meters/day
  • Labor: 4 workers (2 skilled, 2 helpers)
  • Duration: Based on total railing length
  1. SS Railing Work
  • Quantity: 6–8 running meters/day
  • Labor: 3 workers
  • Duration: Based on railing length
  1. External Plaster
  • Quantity: 70–100 square meters/day
  • Labor: 5 workers (2 masons, 3 helpers)
  • Duration: Depends on wall surface
  1. Dry Stone Pitching
  • Quantity: 8–10 square meters/day
  • Labor: 4 workers
  • Duration: Based on total area
  1. Laminate Fixing
  • Quantity: 6–8 square meters/day
  • Labor: 2 carpenters, 1 helper
  • Duration: Based on laminate area
  1. Gypsum Board Partition Fixing
  • Quantity: 20–25 square meters/day
  • Labor: 3 workers
  • Duration: Based on partition area
  1. Veneer Paneling
  • Quantity: 5–8 square meters/day
  • Labor: 2 carpenters, 1 helper
  • Duration: Based on total area
  1. Pelmet Installation (300 mm)
  • Quantity: 10–12 running meters/day
  • Labor: 2 carpenters, 1 helper
  • Duration: Based on total length
  1. Rolling Shutter Installation (3M x 3M)
  • Quantity: 1–2 shutters/day
  • Labor: 4 workers (2 fitters, 2 helpers)
  • Duration: Based on total shutters
  1. MS Work - Fabrication
  • Quantity: 150–200 kilograms/day
  • Labor: 5 workers
  • Duration: Based on total weight
  1. MS Work - Installation
  • Quantity: 200–300 kilograms/day
  • Labor: 5 workers
  • Duration: Based on total weight
  1. Tremix Flooring
  • Quantity: 40–50 square meters/day
  • Labor: 4 workers
  • Duration: Depends on floor area
  1. Vitrified Tile Flooring
  • Quantity: 15–20 square meters/day
  • Labor: 3 workers (2 masons, 1 helper)
  • Duration: Based on total area
  1. Ceramic Tile Flooring
  • Quantity: 15–20 square meters/day
  • Labor: 3 workers (2 masons, 1 helper)
  • Duration: Based on flooring area
  1. Counter Top Stone Fixing
  • Quantity: 4–6 countertops/day
  • Labor: 3 workers (1 mason, 2 helpers)
  • Duration: Based on total countertops
  1. Stone Edge Moulding
  • Quantity: 10–12 running meters/day
  • Labor: 2 workers
  • Duration: Based on edge length
  1. Floor Polishing
  • Quantity: 30–40 square meters/day
  • Labor: 3 workers (2 polishers, 1 helper)
  • Duration: Based on floor area
  1. POP Floor Protection
  • Quantity: 50–60 square meters/day
  • Labor: 2 workers
  • Duration: Depends on total area
  1. PVC Sheet Floor Protection
  • Quantity: 70–80 square meters/day
  • Labor: 2 workers
  • Duration: Based on total area
  1. Installation of Sanitary Fixtures
  • Quantity: 6–8 fixtures/day
  • Labor: 2 plumbers, 1 helper
  • Duration: Based on total fixtures
  1. Installation of Chinaware
  • Quantity: 5–7 units/day
  • Labor: 3 workers (2 plumbers, 1 helper)
  • Duration: Based on units
  1. Installation of Concealed Items
  • Quantity: 5–7 units/day
  • Labor: 3 workers
  • Duration: Depends on concealed units
  1. Fixing of Toilet Cubicle/Partition
  • Quantity: 3–5 cubicles/day
  • Labor: 4 workers
  • Duration: Based on total cubicles
  1. Installation of Toilet Accessories/Machinery Equipment
  • Quantity: 6–8 units/day
  • Labor: 3 workers (2 plumbers, 1 helper)
  • Duration: Based on equipment
  1. CPVC Pipe Laying
  • Quantity: 60–80 running meters/day
  • Labor: 4 workers
  • Duration: Based on total length
  1. UPVC Pipe Laying
  • Quantity: 50–70 running meters/day
  • Labor: 4 workers
  • Duration: Based on pipe length
  1. G.I. Pipe Laying
  • Quantity: 50–70 running meters/day
  • Labor: 4 workers (2 skilled, 2 helpers)
  • Duration: Based on pipe length
  1. Copper Pipe Laying
  • Quantity: 40–50 running meters/day
  • Labor: 3 workers (1 skilled, 2 helpers)
  • Duration: Based on pipe length
  1. DWC Pipe Laying
  • Quantity: 80–100 running meters/day
  • Labor: 5 workers (2 skilled, 3 helpers)
  • Duration: Based on total length
  1. HDPE Pipe Laying
  • Quantity: 70–90 running meters/day
  • Labor: 4 workers
  • Duration: Depends on total pipe length
  1. RCC Pipe Laying
  • Quantity: 25–30 running meters/day
  • Labor: 6 workers (2 skilled, 4 helpers)
  • Duration: Based on total length
  1. C.I. Pipe Laying
  • Quantity: 30–40 running meters/day
  • Labor: 4 workers
  • Duration: Based on pipe length
  1. SS Pipe Laying
  • Quantity: 30–40 running meters/day
  • Labor: 4 workers (2 skilled, 2 helpers)
  • Duration: Based on total length
  1. Plumbing 1st Fix
  • Quantity: 3–5 points/day
  • Labor: 2 plumbers, 1 helper
  • Duration: Based on total points
  1. Trap Fixing
  • Quantity: 6–8 traps/day
  • Labor: 3 workers (2 plumbers, 1 helper)
  • Duration: Based on total traps
  1. Fixing of Floor Drain
  • Quantity: 8–10 drains/day
  • Labor: 2 workers
  • Duration: Based on total drains
  1. Thermal Insulation of Pipes
  • Quantity: 50–70 running meters/day
  • Labor: 3 workers (2 skilled, 1 helper)
  • Duration: Based on total length
  1. Cinder Raised Flooring
  • Quantity: 15–20 square meters/day
  • Labor: 5 workers
  • Duration: Based on area
  1. Modular Access Raised Flooring
  • Quantity: 25–30 square meters/day
  • Labor: 4 workers (2 skilled, 2 helpers)
  • Duration: Based on total area
  1. Installation of Water Flow Meter
  • Quantity: 4–6 meters/day
  • Labor: 2 plumbers, 1 helper
  • Duration: Based on meters
  1. Gully Trap Fixing
  • Quantity: 8–10 traps/day
  • Labor: 3 workers (2 masons, 1 helper)
  • Duration: Based on traps
  1. Excavation for External Plumbing
  • Quantity: 10–15 cubic meters/day
  • Labor: 4 workers (2 skilled, 2 helpers)
  • Duration: Based on trench volume
  1. Haunching
  • Quantity: 12–15 running meters/day
  • Labor: 3 workers
  • Duration: Based on haunch length
  1. Paver Block Laying
  • Quantity: 20–25 square meters/day
  • Labor: 4 workers (2 masons, 2 helpers)
  • Duration: Based on area
  1. Manhole Construction
  • Quantity: 1–2 manholes/day
  • Labor: 5 workers (2 masons, 3 helpers)
  • Duration: Based on number of manholes
  1. Catch Basin Construction
  • Quantity: 1 basin/day
  • Labor: 4 workers
  • Duration: Based on number of basins
  1. Rainwater Harvesting Pit Construction
  • Quantity: 1 pit/day
  • Labor: 6 workers
  • Duration: Based on number of pits
  1. De-Silting Chamber Construction
  • Quantity: 1 chamber/day
  • Labor: 4 workers (2 skilled, 2 helpers)
  • Duration: Based on total chambers
  1. Manhole SFRC Frame & Cover Fixing
  • Quantity: 2–3 covers/day
  • Labor: 3 workers
  • Duration: Based on total covers
  1. Manhole D.I. Frame & Cover Fixing
  • Quantity: 2–3 covers/day
  • Labor: 3 workers
  • Duration: Based on total covers
  1. Installation of Sump Pump
  • Quantity: 1–2 pumps/day
  • Labor: 4 workers (2 skilled, 2 helpers)
  • Duration: Based on number of pumps
  1. Installation of Fire Pump
  • Quantity: 1 pump/day
  • Labor: 5 workers (2 skilled, 3 helpers)
  • Duration: Based on total pumps
  1. Installation of Plumbing Water Supply Pump
  • Quantity: 1–2 pumps/day
  • Labor: 4 workers (2 skilled, 2 helpers)
  • Duration: Based on number of pumps
  1. Installation of Domestic Water Submersible Pump
  • Quantity: 1–2 pumps/day
  • Labor: 4 workers
  • Duration: Based on total pumps
  1. Making Connection of Sewer Line with Municipality Line
  • Quantity: 1 connection/day
  • Labor: 6 workers (3 skilled, 3 helpers)
  • Duration: Based on connections
  1. Making Connection of Sewer Line with STP
  • Quantity: 1 connection/day
  • Labor: 6 workers (3 skilled, 3 helpers)
  • Duration: Based on total connections
  1. Making Connection of Raw Water Supply Line with Municipality Line
  • Quantity: 1 connection/day
  • Labor: 6 workers (3 skilled, 3 helpers)
  • Duration: Based on connections
  1. Plywood Raised Flooring
  • Quantity: 20–25 square meters/day
  • Labor: 4 workers (2 carpenters, 2 helpers)
  • Duration: Based on area
  1. Artificial Grass Flooring
  • Quantity: 25–30 square meters/day
  • Labor: 3 workers (1 skilled, 2 helpers)
  • Duration: Based on total area
  1. Letter Box Fixing at Boundary Wall
  • Quantity: 4–6 boxes/day
  • Labor: 2 workers
  • Duration: Based on number of boxes
  1. FM2 Flooring
  • Quantity: 100–150 square meters/day
  • Labor: 10 workers (3 masons, 7 helpers)
  • Duration: Based on total area
  1. Electrical 1st Fix (Conduiting)
  • Quantity: 40–50 meters/day
  • Labor: 5 workers (2 electricians, 3 helpers)
  • Duration: Based on total conduits
  1. Electrical 2nd Fix (Wiring)
  • Quantity: 40–50 meters/day
  • Labor: 4 workers (2 electricians, 2 helpers)
  • Duration: Based on total wiring
  1. Electrical Fixtures Installation
  • Quantity: 10–15 fixtures/day
  • Labor: 3 workers (1 electrician, 2 helpers)
  • Duration: Based on total fixtures
  1. Electrical 1st Fix (Modular Box Fixing)
  • Quantity: 25–30 boxes/day
  • Labor: 4 workers
  • Duration: Based on total boxes
  1. DG Commissioning
  • Quantity: 1 DG/day
  • Labor: 6 workers (2 skilled, 4 helpers)
  • Duration: Based on total DG units
  1. Installation of LT & LV Equipment
  • Quantity: 2–3 units/day
  • Labor: 5 workers (2 skilled, 3 helpers)
  • Duration: Based on total equipment
  1. Electrical 1st Fix (Cable Tray Installation)
  • Quantity: 30–40 meters/day
  • Labor: 5 workers (2 skilled, 3 helpers)
  • Duration: Based on total cable tray length
  1. Electrical 1st Fix (Raceway)
  • Quantity: 25–30 meters/day
  • Labor: 5 workers (2 skilled, 3 helpers)
  • Duration: Based on total raceway length
  1. HVAC 1st Fix (Ducting/Copper Pipe Laying)
  • Quantity: 20–30 meters/day
  • Labor: 4 workers (2 skilled, 2 helpers)
  • Duration: Based on total ducting
  1. HVAC 2nd Fix (Insulation)
  • Quantity: 40–50 meters/day
  • Labor: 3 workers (1 skilled, 2 helpers)
  • Duration: Based on total insulation length
  1. Installation of HVAC Equipment
  • Quantity: 2–3 units/day
  • Labor: 5 workers (3 skilled, 2 helpers)
  • Duration: Based on total equipment
  1. Installation of HVAC Fixtures
  • Quantity: 3–5 fixtures/day
  • Labor: 4 workers
  • Duration: Based on total fixtures
  1. Fixing of Acoustic Insulation
  • Quantity: 20–30 square meters/day
  • Labor: 3 workers (2 skilled, 1 helper)
  • Duration: Based on total area
  1. Fire Fighting Work Commissioning
  • Quantity: 1 zone/day
  • Labor: 6 workers
  • Duration: Based on zones
  1. Installation of LT & LV Equipment for HVAC Equipment
  • Quantity: 2–3 units/day
  • Labor: 5 workers (3 skilled, 2 helpers)
  • Duration: Based on equipment
  1. Earthing Work
  • Quantity: 4–6 pits/day
  • Labor: 4 workers (2 electricians, 2 helpers)
  • Duration: Based on pits
  1. Layout Work
  • Quantity: 200–250 square meters/day
  • Labor: 2 surveyors
  • Duration: Based on site requirements
  1. Counter Slab
  • Quantity: 3–5 slabs/day
  • Labor: 5 workers (2 masons, 3 helpers)
  • Duration: Based on slabs
  1. RCC Lintel
  • Quantity: 8–10 running meters/day
  • Labor: 6 workers (2 skilled, 4 helpers)
  • Duration: Based on length
  1. RCC Work
  • Quantity: 8–10 cubic meters/day
  • Labor: 10 workers
  • Duration: Based on total quantity
  1. Fire Fighting 1st Fix (Main & Sprinkler Pipe Erection & Welding)
  • Quantity: 30–40 running meters/day
  • Labor: 6 workers (2 welders, 4 helpers)
  • Duration: Based on length
  1. Densification of Flooring
  • Quantity: 100–150 square meters/day
  • Labor: 6 workers
  • Duration: Based on area
  1. ELV 1st Fix (Data & Networking)
  • Quantity: 40–50 meters/day
  • Labor: 4 workers (2 skilled, 2 helpers)
  • Duration: Based on cable length
  1. Furniture Fabrication
  • Quantity: Based on design, typically 1–2 items/day
  • Labor: 5 workers (2 carpenters, 3 helpers)
  • Duration: Based on number and complexity
  1. Tile Cladding
  • Quantity: 20–25 square meters/day
  • Labor: 4 workers (2 masons, 2 helpers)
  • Duration: Based on area
  1. Wall Cladding
  • Quantity: 15–20 square meters/day
  • Labor: 5 workers (3 skilled, 2 helpers)
  • Duration: Based on total area
  1. POP False Ceiling
  • Quantity: 20–25 square meters/day
  • Labor: 5 workers (2 skilled, 3 helpers)
  • Duration: Based on total ceiling area
  1. CCTV Installation
  • Quantity: 6–8 cameras/day
  • Labor: 4 workers (2 technicians, 2 helpers)
  • Duration: Based on total cameras
  1. Greenery Plantation
  • Quantity: 15–20 saplings/day
  • Labor: 4 workers (2 gardeners, 2 helpers)
  • Duration: Based on total saplings
  1. ELV Fixtures
  • Quantity: 8–10 fixtures/day
  • Labor: 3 workers (2 skilled, 1 helper)
  • Duration: Based on total fixtures
  1. Epoxy Flooring
  • Quantity: 80–100 square meters/day
  • Labor: 5 workers (2 skilled, 3 helpers)
  • Duration: Based on total area
  1. RO Installation
  • Quantity: 1–2 units/day
  • Labor: 3 workers (2 skilled, 1 helper)
  • Duration: Based on units
  1. Hob Installation
  • Quantity: 1–2 hobs/day
  • Labor: 3 workers (1 skilled, 2 helpers)
  • Duration: Based on units
  1. Chimney Installation
  • Quantity: 1–2 chimneys/day
  • Labor: 3 workers (1 skilled, 2 helpers)
  • Duration: Based on total units
  1. Geyser Installation
  • Quantity: 2–3 geysers/day
  • Labor: 2 workers
  • Duration: Based on units
  1. Facade Textured Paint
  • Quantity: 60–80 square meters/day
  • Labor: 4 workers (2 painters, 2 helpers)
  • Duration: Based on total area
  1. Fire Fighting 2nd Fix
  • Quantity: 20–25 fixtures/day
  • Labor: 6 workers (3 skilled, 3 helpers)
  • Duration: Based on fixtures
  1. Plumbing 2nd Fix
  • Quantity: 10–15 fixtures/day
  • Labor: 4 workers (2 plumbers, 2 helpers)
  • Duration: Based on total plumbing
  1. ELV 2nd Fix
  • Quantity: 8–10 fixtures/day
  • Labor: 4 workers
  • Duration: Based on total installations
  1. Deshuttering
  • Quantity: 10–15 cubic meters/day
  • Labor: 6 workers (2 skilled, 4 helpers)
  • Duration: Based on total structure
  1. PVC Flooring
  • Quantity: 50–60 square meters/day
  • Labor: 4 workers (2 skilled, 2 helpers)
  • Duration: Based on total area
  1. Wooden Skirting
  • Quantity: 50–60 running meters/day
  • Labor: 4 workers (2 skilled, 2 helpers)
  • Duration: Based on length
  1. Fire Fighting Fixtures Installation
  • Quantity: 8–10 fixtures/day
  • Labor: 4 workers
  • Duration: Based on fixtures
  1. Wallpaper Fixing
  • Quantity: 20–25 square meters/day
  • Labor: 3 workers (2 skilled, 1 helper)
  • Duration: Based on total area
  1. Formwork - Mivan Shuttering
  • Quantity: 60–80 square meters/day
  • Labor: 8 workers (4 skilled, 4 helpers)
  • Duration: Based on total formwork
  1. DB Installation
  • Quantity: 2–3 DBs/day
  • Labor: 4 workers (2 skilled, 2 helpers)
  • Duration: Based on total boards
  1. Slab Cutting
  • Quantity: 10–15 square meters/day
  • Labor: 6 workers (2 skilled, 4 helpers)
  • Duration: Based on cutting size
  1. Road-WBM Laying
  • Quantity: 150–200 square meters/day
  • Labor: 10 workers (4 skilled, 6 helpers)
  • Duration: Based on total area
  1. Geotextile Membrane Laying
  • Quantity: 100–150 square meters/day
  • Labor: 6 workers
  • Duration: Based on total length
  1. External Plumbing
  • Quantity: 30–40 meters/day
  • Labor: 5 workers (2 plumbers, 3 helpers)
  • Duration: Based on total length
  1. Wall Framing Work
  • Quantity: 20–25 square meters/day
  • Labor: 6 workers (3 carpenters, 3 helpers)
  • Duration: Based on total area
  1. External Drainage Line Testing
  • Quantity: 40–50 meters/day
  • Labor: 5 workers
  • Duration: Based on pipe length
  1. Fire Alarm System Panel & Connection Checking
  • Quantity: 1–2 panels/day
  • Labor: 4 workers (2 electricians, 2 helpers)
  • Duration: Based on number of panels
  1. Firefighting Commissioning
  • Quantity: Based on system size, typically 1 zone/day
  • Labor: 6 workers (3 skilled, 3 helpers)
  • Duration: Based on zones/system size
  1. Chain Link Fencing
  • Quantity: 20–30 running meters/day
  • Labor: 6 workers (2 welders, 4 helpers)
  • Duration: Based on total length
  1. Beading Installation
  • Quantity: 30–40 running meters/day
  • Labor: 4 workers (2 skilled, 2 helpers)
  • Duration: Based on total beading length
  1. Sliding Door Installation
  • Quantity: 1–2 doors/day
  • Labor: 4 workers (2 skilled, 2 helpers)
  • Duration: Based on total doors
  1. Road-Subgrade Preparation
  • Quantity: 150–200 square meters/day
  • Labor: 10 workers (4 skilled, 6 helpers)
  • Duration: Based on road area
  1. HVAC Work Testing & Commissioning
  • Quantity: Based on system size, 1 zone/day
  • Labor: 6 workers (3 skilled, 3 helpers)
  • Duration: Based on HVAC zones
  1. Mangalore Tile Fixing
  • Quantity: 50–70 square meters/day
  • Labor: 6 workers (2 masons, 4 helpers)
  • Duration: Based on roof area
  1. Electrical Work Commissioning
  • Quantity: Based on scope, 1–2 DBs/day
  • Labor: 6 workers (3 electricians, 3 helpers)
  • Duration: Based on DB count
  1. Cleaning and Flushing of Pipes
  • Quantity: 30–40 meters/day
  • Labor: 5 workers (3 plumbers, 2 helpers)
  • Duration: Based on pipe length
  1. Lift Installation
  • Quantity: 1 lift/10–15 days
  • Labor: 8 workers (4 technicians, 4 helpers)
  • Duration: Based on total lifts
  1. Band RCC
  • Quantity: 10–15 cubic meters/day
  • Labor: 8 workers (4 masons, 4 helpers)
  • Duration: Based on RCC quantity
  1. Grating Installation
  • Quantity: 15–20 square meters/day
  • Labor: 6 workers (3 welders, 3 helpers)
  • Duration: Based on area
  1. Electrical HT Panel Installation
  • Quantity: 1 panel/day
  • Labor: 6 workers (3 electricians, 3 helpers)
  • Duration: Based on panels
  1. Transformer Commissioning
  • Quantity: 1 transformer/3–4 days
  • Labor: 10 workers (4 electricians, 6 helpers)
  • Duration: Based on total transformers
  1. GSB Laying
  • Quantity: 200–250 square meters/day
  • Labor: 10 workers (4 skilled, 6 helpers)
  • Duration: Based on total road area
  1. Neat Cement Flooring
  • Quantity: 60–80 square meters/day
  • Labor: 6 workers (2 masons, 4 helpers)
  • Duration: Based on total flooring
  1. Mirror Fixing
  • Quantity: 10–15 mirrors/day
  • Labor: 4 workers (2 skilled, 2 helpers)
  • Duration: Based on mirrors
  1. Backlit Corian Fixing
  • Quantity: 10–12 square meters/day
  • Labor: 5 workers (2 skilled, 3 helpers)
  • Duration: Based on total area
  1. De-Snagging
  • Quantity: Based on defects, typically 1 zone/day
  • Labor: 4–6 workers (2 skilled, 4 helpers)
  • Duration: Based on scope
  1. STP Commissioning
  • Quantity: 1 plant/7–10 days
  • Labor: 10 workers (5 technicians, 5 helpers)
  • Duration: Based on plant size
  1. Barbeque Installation
  • Quantity: 1 barbeque/day
  • Labor: 4 workers (2 skilled, 2 helpers)
  • Duration: Based on total units
  1. Vinyl Flooring
  • Quantity: 50–60 square meters/day
  • Labor: 4 workers (2 skilled, 2 helpers)
  • Duration: Based on total area
  1. OHT Installation
  • Quantity: 1 tank/3–4 days
  • Labor: 8 workers (4 technicians, 4 helpers)
  • Duration: Based on tanks
  1. Modular Kitchen Installation
  • Quantity: 1 kitchen/3–5 days
  • Labor: 6 workers (3 skilled, 3 helpers)
  • Duration: Based on total kitchens
  1. Dismantling
  • Quantity: 10–15 square meters/day
  • Labor: 6 workers (2 skilled, 4 helpers)
  • Duration: Based on scope
  1. Signage Installation
  • Quantity: 1–2 signages/day
  • Labor: 4 workers (2 skilled, 2 helpers)
  • Duration: Based on signages
  1. ELV Work Commissioning
  • Quantity: 1 zone/day
  • Labor: 6 workers (3 skilled, 3 helpers)
  • Duration: Based on zones
  1. Plumbing Work Commissioning
  • Quantity: Based on system size, typically 1 zone/day
  • Labor: 6 workers (3 skilled, 3 helpers)
  • Duration: Based on scope
  1. CBG Installation
  • Quantity: 1 unit/day
  • Labor: 6 workers (3 technicians, 3 helpers)
  • Duration: Based on units

Comments

Popular posts from this blog

CPWD specifications Vol. 1 & Vol. 2 ( 2009 )

  CPWD specifications  Vol. 1 & Vol. 2  ( 2009 ) Download Vol. 1  Click here Download Vol. 2 Click here Thanks for  reading this article. If you find this article helpful please, don’t forget to share and  Subscribe  Afroz Civil website and YouTube Channel for Latest Update. I hope this check list points will be helpful for every site Engineer. 😍Join Our YouTube Channel   Click here    😍Join Our WhatsApp Group   Click here I always Update helpful information and share my practical experience at this site. Please Give your feedback in comment box.

GENERAL NOTES AND STANDARD DETAILS ( FOR RCC CONSTRUCTION) MISCELLANEOUS TYPICAL DETAILS PDF

GENERAL NOTES AND STANDARD DETAILS ( FOR R.C.C CONSTRUCTION)  MISCELLANEOUS TYPICAL DETAILS PDF #GENERAL NOTES FOR  RCC STRUCTURE (SHEET 3 OF 3) Thanks for download and reading this drawing . If you find this Drawing  helpful please, don’t forget to share and  Subscribe  Afroz Civil website and YouTube Channel for Latest Update. I hope this drawing will be helpful for every site Engineer. I always Update helpful information and share my practical experience at this site & on our YouTube Channel. Download this drawing in Pdf     Click here Join Our YouTube Channel   Click here    Join Our WhatsApp Group   Click here Please Give your feedback in comment box. I always Update helpful information and share my practical experience at this site. Please Give your feedback in comment box.

TEST REPORT of DESIGN MIX M-30 & M-25

        Sample -1 M25          Sample -2 M25              Sample -3 M25            Sample -1 M30 Sample -2  M30