Rate Analysis Excel Sheet Download | AOR, SOR, DSR Templates – Afroz Civil
Rate Analysis, Civil Engineering, AOR, SOR, DAR, Labour Output Constants, Construction Estimation, Costing, Billing, Material Cost, Machinery Cost, Afroz Civil
Rate Analysis in civil engineering is a complete scientific method used to calculate the actual unit cost of construction activities. A proper rate analysis includes the breakdown of material, labour, machinery, overheads, contractor profit, taxes, and productivity norms. Accurate rate analysis ensures transparent billing, precise estimation, cost control, and efficient project management.
It forms the foundation of the Analysis of Rates (AOR) and aligns with the Schedule of Rates (SOR/DAR) published by CPWD, PWD and State Engineering Departments. These codes help engineers maintain standard, uniform and technically correct cost calculations across all construction activities.
Abbreviations Used in Rate Analysis:
In this article, several important engineering abbreviations have been used, and each plays a key role in preparing accurate construction costing. AOR (Analysis of Rates) defines the method for calculating the detailed cost of every activity, while SOR (Schedule of Rates) and DAR (Delhi Analysis of Rates) provide approved departmental rates for materials, labour and machinery. The DSR (Delhi Schedule of Rates) issued by the CPWD (Central Public Works Department) and different PWDs (Public Works Departments) ensures standardised costing across government projects. Labour productivity is based on IS 7272 – Indian Standard Recommendation for Labour Output Constants, which specifies daily output norms for masons, labourers and work teams. Costing and billing rely on a well-prepared BOQ (Bill of Quantities) and regular RA Bills (Running Account Bills). Larger projects also require a DPR (Detailed Project Report), supported by accurate T&P (Tools and Plants) allocation and applicable GST (Goods and Services Tax). These full forms and standards help maintain clarity, transparency and correctness in Rate Analysis and civil engineering estimation.
Purpose of Rate Analysis
-
Determine realistic unit rates for BOQ items
-
Standardize costs as per AOR / SOR / DAR
-
Evaluate contractor claims and prevent overbilling
-
Plan labour and machinery based on productivity norms
-
Support detailed technical and financial estimates
-
Ensure compliance with CPWD / PWD specifications
-
Maintain cost transparency during tendering
-
Support DPR preparation & cost justification
-
Compare market rates vs departmental rates
-
Improve project cost control and decision-making
Main Components of Rate Analysis
1. Material Cost (With SOR/DAR Coefficients)
Material quantities are derived using standard engineering formulas and SOR/DAR material coefficients.
Includes:
-
Cement, sand, aggregates
-
Steel reinforcement
-
Bricks and blocks
-
Finishing materials
-
Wastage allowance (typically 2–5%)
-
Loading/Unloading/Transportation
Material rates must match SOR/DAR or latest local market analysis.
2. Labour Cost (As per Wage Code + SOR/DAR Rates)
Labour wages depend on:
-
Skilled, semi-skilled & unskilled categories
-
Minimum Wages Act
-
DAR/DSR wage tables
-
Productivity norms
Labour requirement is calculated using output constants (DAR norms).
3. Labour Output Constants - IS 7272 (Part -1 ) 1974
Labour Output Constants (as per Delhi Analysis of Rate (DAR) Labour Productivity Tables) define how much work one labourer or mason can complete in 1 day.
Standard Output Constants (DAR norms):
-
Earthwork Excavation: 3–5 m³ per mazdoor/day
-
Brickwork: 1.0–1.25 m³ per mason/day
-
Plastering: 8–10 m² per mason/day
-
Concrete Work: 1.5–2 m³ per labour team/day
-
Shuttering Removal: 10–12 m² per helper/day
-
Formwork Fixing: 5–7 m² per carpenter/day
-
Reinforcement Steel Cutting/Bending: 50–70 kg per fitter/day
These constants directly determine labour quantity and labour cost.
4. Machinery / Equipment Cost (AOR & DAR Based)
Machinery cost includes:
-
Excavators, JCB
-
Rollers, compactors
-
Tractor trolleys
-
Concrete mixers
-
Pumps and generators
DAR provides equipment hourly output which must be used:
Cost = (Hourly rate × Working hours) + Fuel + Operator
5. Lead, Lift, Carriage & Handling
As per DAR/SOR:
-
Lead = Horizontal transportation distance
-
Lift = Vertical movement
-
Carriage rates = Government-approved
-
Loading/Unloading allowances
Earthwork, concrete, sand, metal & brick transportation charges vary significantly based on lead distances.
6. Overheads, Contractor Profit & Taxes
Departmental norms (DAR/PWD/CPWD):
-
10–15% Overheads
-
10–15% Contractor Profit
-
GST as applicable
-
Safety & T&P charges
-
Site establishment cost
Additional Components of Rate Analysis
7. Site Conditions
Cost varies due to:
-
Soil type
-
Water table level
-
Accessibility
-
Weather conditions
-
Site layout
8. Productivity of Labour & Machines
Lower productivity = Higher cost
Higher productivity = Lower cost
9. Risk Factor / Contingencies
Usually 3–5% added in major infrastructure projects.
10. Quality Requirements
Higher quality standards increase:
-
Material consumption
-
Skilled labour requirement
-
Equipment usage
11. Duration of Work
Fast-track projects cost more due to overtime and extra machinery.
12. Local Market Fluctuation
Cement, steel, diesel prices change frequently and affect rate analysis.
Rate Analysis as per SOR / DAR
SOR/DAR documents include:
-
Material basic rates
-
Labour wage rates
-
Standard outputs
-
Coefficients
-
Equipment productivity
-
Approved unit rates
Using DAR ensures:
✔ Accurate
✔ Auditable
✔ Transparent
✔ Accepted by all departments
✔ Technically correct as per civil engineering norms
Importance of Rate Analysis in Civil Engineering
-
Ensures fair & transparent billing
-
Helps in accurate estimation & DPR
-
Supports Project Managers in resource planning
-
Helps Consultants justify technical rates
-
Useful for Billing Engineers during RA bill checking
-
Provides clarity to Clients/Owners
-
Avoids disputes between contractor & engineer
-
Improves overall project cost control
Rate Analysis at Afroz Civil
Afroz Civil prepares Rate Analysis using:
-
Delhi Analysis of Rates (DAR)
-
CPWD Labour Output Standards
-
AOR (Analysis of Rates) methods
-
Real market material rates
-
Updated machinery productivity norms
Our Rate Analysis Bundle covers Excavation to Finishing Work, making it ideal for:
-
Billing Engineers
-
Project Managers
-
Consultants
-
Contractors
-
Clients
Download Rate Analysis Excel Sheet (AOR + SOR) Templates
Get professionally designed Excel sheets for Rate Analysis, Estimation, BOQ, Billing, DPR, Labour Management and Construction Planning. Perfect for Billing Engineers, Project Managers, Consultants and Contractors.
👉 Download Now:
Click Here https://rzp.io/rzp/DKNgZTPZ
watch the excel template folder
ChatGPT AI Prompt
🎁 BONUS FOR YOU:
You can use this prompt to instantly find any BOQ item from DAR/DSR 2023.
Just change the activity name and press enter — ChatGPT will give you the exact DSR item number + full specification, perfect for Billing Engineers, QS, Estimation & Tendering Work.
BOQ Item Finder Prompt:
"From the Delhi Analysis of Rates (DAR/DSR 2023), give the exact item number and description/activity name for the activity "[enter name of activity here]", exactly as written in the DSR book.
Do not include any explanation, summary, or notes — only return the item number and full description as per the DSR format"
You can also watch the complete Rate Analysis process step-by-step on Afroz Civil.