Comprehensive Productivity and Labor Estimation for Construction Activities
This is the productivity of construction works, including quantity, labor, and duration, which is very helpful information for all site engineers. Productivity, Labor, and Duration for Activities Excavation (Manual) Quantity : 8–10 cubic meters/day per laborer Labor : 10–15 laborers (for larger sites) Duration : As per the area/volume to excavate Mechanical Excavation Quantity : 80–120 cubic meters/day (using an excavator) Labor : 1 operator, 2 helpers Duration : Based on excavation size Manual Backfilling from Available Soil Quantity : 12 cubic meters/labor/day Labor : 6–8 laborers Duration : Based on total area/volume Backfilling from Brought-Out Soil Quantity : 15 cubic meters/labor/day Labor : 5 laborers (excluding transport equipment labor) Duration : Based on volume and transport logistics Sand Filling Quantity : 20 cubic meters/day (manual filling) Labor : 4–5 laborers Duration : Based on area and thickness Anti-Termite Treatment Quantity : 1,000–1,200 square meters/day (spray a...