Rate Analysis of Centering & Shuttering for Footings – DAR 2023 (Item 4.3.1)



As per Delhi Analysis of Rates (DAR), Volume–01, 2023 | Page 168

Afroz Civil presents a ready-to-use Excel Rate Analysis Template for Centering and Shuttering work, including strutting, propping, staging, and removal of formwork, applicable for foundations, footings, and column bases, prepared strictly as per DAR 2023, Item 4.3.1.

This rate analysis is developed using practical site assumptions and is ideal for estimation, billing, BOQ preparation, tendering, and live project execution.


Scope of Work Covered

  • Centering and shuttering including strutting, propping, and staging

  • Formwork for foundations, footings, and column bases

  • Removal of formwork after completion of concreting

  • Rate derived based on contact area (shuttering area)


Footing Details Considered

  • Footing Size: 2.5 m × 2.5 m × 1.0 m

  • Shuttering Area Considered: 10.8 SQM

  • Unit: Per Square Metre (SQM)

The analysis is structured so that the final rate per SQM can be directly applied to any project.


Material Cost Considered (System Shuttering)

The analysis includes detailed costing of commonly used shuttering materials:

  • Wall form panels (1250 × 500 mm)

  • Corner angles

  • Channel shoulders

  • Double clips (bridge clips)

  • Single clips

  • MS tubes (40 mm diameter)

  • Assembly nuts and bolts

Practical Assumptions Used

  • Shuttering material assumed usable for 40 repetitions

  • 10% maintenance cost included

  • Salvage value taken @ 25% after full usage

These assumptions reflect real site practices, ensuring accurate and realistic costing.


Labour Cost Included

Labour rates are taken as per DAR 2023, including:

  • Fitter (Grade–1)

  • Beldar

Labour productivity has been considered practically for site execution.


Carriage, Equipment & Miscellaneous

  • Material carriage included

  • Shuttering oil included

  • Sundries considered

  • Water charges @ 1% added as per standard practice


Contractor’s Profit & Overheads

  • 15% contractor’s profit and overheads added

  • Transparent step-by-step calculation


Final Cost Summary

  • Total cost for 10.8 SQM: ₹3,177 (Say)

  • Rate per 1 SQM of shuttering: ₹317.70

This rate can be directly used for:

  • BOQ preparation

  • RA & final billing

  • Tender rate justification

  • Site planning and cost control


Key Features

  • ✔ Fully compliant with DAR 2023 (Item 4.3.1)

  • ✔ Detailed material, labour & equipment breakup

  • Auto-calculation Excel format

  • Yellow-highlighted input cells for easy data entry

  • ✔ Practical and editable template for site use


👉 Download Rate Analysis of Centering & Shuttering for Footings – DAR 2023 (Item 4.3.1)
(Excel Sheet as shown in the above images)

Price: ₹19 only

Enter your site data and get instant, accurate results.

Download Now


Important Note

Please enter current market rates for materials, carriage, labour, and equipment, or use the latest applicable SOR/DSR, to achieve the most accurate results.


If You Find Rate Analysis of of Centering & Shuttering for Footings Helpful

Pay ₹39 only and get access to all Rate Analysis Excel Sheets including:

  • Foundation Excel Sheet Template

  • Column Excel Sheet Template

  • Beam Excel Sheet Template

  • Staircase Excel Sheet Template

Practical, editable templates ready for site use.

Download Now

Afroz Civil

Practical Civil Engineering • Real Site Knowledge

You can also watch the complete Rate Analysis process step-by-step on Afroz Civil


Customer Support Desk- Click Here


Thanks

Afroz Civil Team

Comments

Popular posts from this blog

IS 1200 All Parts (1 to 28) – Free Download PDF for Site Engineers & Billing

Method of Measurement IS Codes – Afroz Civil 👷 Introduction In civil engineering projects, measurement is the foundation for estimation, costing, billing, and project planning . Without a standard method, every engineer or contractor may interpret work differently. To remove this confusion, the Bureau of Indian Standards (BIS) published IS 1200 – Method of Measurement of Building & Civil Engineering Works . These codes ensure uniformity, transparency, and accuracy in construction measurement. Whether you are a Site Engineer, Billing Engineer, Project Manager, Contractor, or Client , IS 1200 is a must-have reference. At Afroz Civil , we have compiled the complete list of IS 1200 parts with free PDF download links so you can easily save them in your Laptop/PC and use them whenever required on site. 📚 IS 1200 – Method of Measurement (All Parts) IS Code Part Work Description Download Link (PDF) IS1200 Part 1 Earthwork Download PDF IS 1200 Part 2 Concr...

Rate Analysis Excel Sheet Download | AOR, SOR, DSR Templates – Afroz Civil

About Rate Analysis   Rate Analysis, Civil Engineering, AOR, SOR, DAR, Labour Output Constants, Construction Estimation, Costing, Billing, Material Cost, Machinery Cost, Afroz Civil Rate Analysis in civil engineering is a complete scientific method used to calculate the actual unit cost of construction activities. A proper rate analysis includes the breakdown of material, labour, machinery, overheads, contractor profit, taxes , and productivity norms. Accurate rate analysis ensures transparent billing , precise estimation , cost control , and efficient project management . It forms the foundation of the Analysis of Rates (AOR) and aligns with the Schedule of Rates (SOR/DAR) published by CPWD, PWD and State Engineering Departments. These codes help engineers maintain standard, uniform and technically correct cost calculations across all construction activities. Abbreviations Used in Rate Analysis: In this article, several important engineering abbreviations have been used, an...

Fire Safety Norms as per NBC

Fire Safety Norms - NBC 2016 | Afroz Civil Fire Safety Norms as per NBC 2016 – Part 4: Fire and Life Safety At Afroz Civil , we ensure your projects comply with the National Building Code (NBC) 2016, Part 4 – Fire and Life Safety. This guide outlines mandatory provisions for fire prevention, protection, and safe evacuation, designed for architects, engineers, and developers. 1. Building Classification by Occupancy Buildings are categorized by their use, each requiring specific fire safety measures: Group A : Residential Group B : Educational Group C : Institutional Group D : Assembly Group E : Business Group F : Mercantile Group G : Industrial Group H : Storage Group I : Haza...

Social Media