Rate Analysis of Centering & Shuttering for Footings – DAR 2023 (Item 4.3.1)
As per Delhi Analysis of Rates (DAR), Volume–01, 2023 | Page 168
Afroz Civil presents a ready-to-use Excel Rate Analysis Template for Centering and Shuttering work, including strutting, propping, staging, and removal of formwork, applicable for foundations, footings, and column bases, prepared strictly as per DAR 2023, Item 4.3.1.
This rate analysis is developed using practical site assumptions and is ideal for estimation, billing, BOQ preparation, tendering, and live project execution.
Scope of Work Covered
Centering and shuttering including strutting, propping, and staging
Formwork for foundations, footings, and column bases
Removal of formwork after completion of concreting
Rate derived based on contact area (shuttering area)
Footing Details Considered
Footing Size: 2.5 m × 2.5 m × 1.0 m
Shuttering Area Considered: 10.8 SQM
Unit: Per Square Metre (SQM)
The analysis is structured so that the final rate per SQM can be directly applied to any project.
Material Cost Considered (System Shuttering)
The analysis includes detailed costing of commonly used shuttering materials:
Wall form panels (1250 × 500 mm)
Corner angles
Channel shoulders
Double clips (bridge clips)
Single clips
MS tubes (40 mm diameter)
Assembly nuts and bolts
Practical Assumptions Used
Shuttering material assumed usable for 40 repetitions
10% maintenance cost included
Salvage value taken @ 25% after full usage
These assumptions reflect real site practices, ensuring accurate and realistic costing.
Labour Cost Included
Labour rates are taken as per DAR 2023, including:
Fitter (Grade–1)
Beldar
Labour productivity has been considered practically for site execution.
Carriage, Equipment & Miscellaneous
Material carriage included
Shuttering oil included
Sundries considered
Water charges @ 1% added as per standard practice
Contractor’s Profit & Overheads
15% contractor’s profit and overheads added
Transparent step-by-step calculation
Final Cost Summary
Total cost for 10.8 SQM: ₹3,177 (Say)
Rate per 1 SQM of shuttering: ₹317.70
This rate can be directly used for:
BOQ preparation
RA & final billing
Tender rate justification
Site planning and cost control
Key Features
✔ Fully compliant with DAR 2023 (Item 4.3.1)
✔ Detailed material, labour & equipment breakup
✔ Auto-calculation Excel format
✔ Yellow-highlighted input cells for easy data entry
✔ Practical and editable template for site use
👉 Download Rate Analysis of Centering & Shuttering for Footings – DAR 2023 (Item 4.3.1)
(Excel Sheet as shown in the above images)
Price: ₹19 only
Enter your site data and get instant, accurate results.
Important Note
Please enter current market rates for materials, carriage, labour, and equipment, or use the latest applicable SOR/DSR, to achieve the most accurate results.
If You Find Rate Analysis of of Centering & Shuttering for Footings Helpful
Pay ₹39 only and get access to all Rate Analysis Excel Sheets including:
Foundation Excel Sheet Template
Column Excel Sheet Template
Beam Excel Sheet Template
Staircase Excel Sheet Template
Practical, editable templates ready for site use.
Afroz Civil
Practical Civil Engineering • Real Site Knowledge
You can also watch the complete Rate Analysis process step-by-step on Afroz Civil
Customer Support Desk- Click Here
Thanks
Afroz Civil Team
.png)
Comments